Capital Improvement Projects
In November 2020, the Board of School Trustees unanimously voted to proceed with a capital improvement project that benefits all CPCSC students. By the time all capital improvements are finished, the project will touch every CPCSC building and provide an upgraded learning environment for all of our students.
Crown Point residents will not see an increase in tax rates because of this project. It is NOT financed by a referendum. The corporation’s existing debt begins to “fall off” over the next three years, allowing the project to be financed via new bonds. There is also additional financial room to pay for other expenses that may come up in future years that are not already financed through the existing operating referendum.
Project Rationale
Planning for this project has been underway for a number of years. Administration and the Board knew they needed to address some important issues that we face at CPCSC:
- Student population growth in the next decade. This is anticipated to be slow growth.
- Overcrowding in classrooms and hallways, especially in secondary schools
- Aging infrastructure and accessibility issues at Taft
- Expanding classroom space and upgrading technology that meets the highest standards of programming and curriculum needs
- Improving common areas like cafeterias, performance spaces, athletic facilities, and playgrounds to be effective and equitable across the district
Building by Building Plans
The timelines and details of the projects may change over the course of construction. We will update information as it becomes available.
- Crown Point High School
- New Taft Middle School
- MacArthur Elementary
- Timothy Ball Elementary
- Lake Street Elementary
- Col. Wheeler Middle School
- Eisenhower Elementary
- Solon Robinson Elementary
- Jerry Ross Elementary
- Winfield Elementary
- Former Taft Site
Crown Point High School
The timeline for construction at CPHS goes through the end of 2024 and will be completed in phases. Included in the renovations:
- Adding 25 new classrooms and 5 new science labs
- Upgrading art, PLTW/robotics, and career/technical education spaces
- Expanding the cafeteria and upgrading the food service program
- Updating the media center
- Using the courtyard to expand administration and guidance spaces
- Widening high-traffic hallways
- Adding rehearsal and storage space to performing arts wing
- Adding indoor physical education space and updating the fitness lab
New Taft Middle School
- New building on 121st Street near Gibson Ave.
- Will be able to accommodate 1500 students.
- Academic wing will include science labs, a media center, and more than 30 classrooms. STEM learning spaces emphasized.
- A Performing Arts wing will provide space for arts and music.
- Two gymnasiums and outdoor spaces will accommodate physical education classes and athletics.
- Timeline: substantially complete before the 2023-2024 school year.
MacArthur Elementary
- 13 new classrooms, including ‘flex’ spaces for instruction and programs
- New stage and a new gymnasium, with more seating for visitors
- STEM space for innovative, 21st century learning
- Refurbished classrooms with technology improvements
- Art, music, special education, media center, and kitchen/cafeteria improvements
- Timeline: substantially complete summer of 2024
Timothy Ball Elementary
- New location for Exceptional Learner preschool classrooms with space for physical therapy and other services
- 13 new classrooms, including ‘flex’ spaces for instruction and programs
- New stage and a new gymnasium, with more seating for visitors
- STEM space for innovative, 21st century learning
- Refurbished classrooms with technology improvements
- Art, music, special education, media center, and kitchen/cafeteria improvements
- Timeline: substantially complete summer of 2024
Lake Street Elementary
Col. Wheeler Middle School
Plans are being finalized to ensure that Wheeler has the same student capacity and features as the new Taft Middle School.
- What is currently the CPCSC Learning Center will be incorporated into the existing Wheeler building. The two buildings will be connected by a new auditorium and elective course classrooms.
- Preschool classrooms currently housed at the Learning Center will move to Timothy Ball, where a special preschool wing will be built.
- Timeline: substantially complete summer of 2024
Eisenhower Elementary
Solon Robinson Elementary
Improvement plans for Solon will begin mid-April 2023. The estimated timeline is substantially complete (80+%) in December 2024, with minor finishes in 2025.
- New front entry (will face north)
- New car rider line – up to 65 cars
- 8 additional classrooms
- New media center
- Stage added to gymnasium
- Expanded bus parking
- New playground
- Storm water management
Jerry Ross Elementary
Winfield Elementary
- Although Winfield completed renovations in 2020, not all parts of the building were addressed in a manor that ensures equal spaces/opportunities for students. Construction will briefly return to Winfield in 2024 to:
- Expand cafeteria and kitchen to be on-par with other schools
- Move media center to previous cafeteria
- Modifications to courtyard
Former Taft Site
- The northernmost portion of Taft will be kept and renovated.
- This will house a number of important programs for the district including CAP, Birth to School, and 18-22 Transition to Adulthood.
- The space will also be used for storage, where all of the items previously stored in the Timothy Ball storage barn will be moved. This is climate-controlled storage, and the barn at Timothy Ball will be removed to make space for better traffic flow.
- On the southern part of the Taft campus, a new administrative building will be constructed. This allows our admin team to be in one building, rather than three. The footprint of the new building will roughly occupy the space that is currently a parking lot on the south side of the existing building.
- Timeline: 2024
Month by Month Progress Updates
- January - May 2025
- January - December 2024
- January - December 2023
- January - December 2022
- November 2020 - December 2021
January - May 2025
January - December 2024
January - December 2023
- November 2023
- October 2023
- September 2023
- August 2023
- July 2023
- May 2023
- April 2023
- February 2023
- January 2023
November 2023
October 2023
September 2023
August 2023
July 2023
May 2023
April 2023
In April, the board approved:
- Landscaping contract at the new Taft
- Agreement for easement to install the new water main at new Taft
- Disposal of hazardous waste from current Taft during demolition
- Cafeteria construction plan at Winfield
For information on the progress at each building this month, please see the board report below.
February 2023
- All construction projects are on time, including the new Taft.
- At CPHS, the performing arts addition is taking shape, and the athletic addition is enclosed.
- Timothy Ball teachers and students moved in to eight new classrooms.
- The administration building will start plumbing, electric, and ductwork soon.
The hallway of the new classroom addition at MacArthur is shown. The new addition is also ready for windows!
January 2023
We are seeing significant progress on our projects throughout the district.
- Teachers at Timothy Ball will begin moving into new classrooms in just a few weeks!
- The new administration space at CPHS will soon receive flooring and light fixtures. The current admin offices will become more space for the cafeteria later this year.
- The auditorium at Wheeler is taking shape. as well as the space connecting Wheeler to the Learning Center.
- We are finalizing plans for Solon and Lake Street Elementary renovations. Stay tuned for more info this spring.
Lockers have been installed at Timothy Ball along with classroom cabinets. Teachers will move in in late February.
January - December 2022
- Nov/Dec 2022
- October 2022
- September 2022
- August 2022
- July 2022
- June 2022
- May 2022
- April 2022
- March 2022
- February 2022
- January 2022
Nov/Dec 2022
October 2022
September 2022
Projects continue to progress on time and on budget. We are in the final steps of approving the more detailed plans for work at Lake Street and Solon. For more detailed information, please see the board report from our partners at Skillman.
Bid packages for Eisenhower Elementary, athletic turf, and the athletic fields were all approved at the September 2022 board meeting.
August 2022
New Robert A. Taft Middle School:
- Completed slab-on-grade in academic wing, piping and storm structures along 121stAvenue, plumbing undergrounds in kitchen area
- Continued roofing of gymnasium and locker room areas, brick veneer on main gymnasium
High School Additions & Renovations:
- Completed CMU foundations for performing arts addition
- Continued hanging mechanical piping in athletic areas running to new athletic addition, above ceiling mechanical work for satellite kitchen
- Began setting structural steel for classroom addition
Timothy Ball Additions & Renovations:
- Completed concrete curbs and walks for west parking lot, setting and detailing structural steel for classroom addition, brick veneer on classroom addition
Douglas MacArthur Additions & Renovations:
- Completed all underground site utilities; demolition of front office, administration, clinic, and music rooms
- Installed and striped binder for southeast parking lot
- Began pouring concrete footings for classroom addition
Colonel Wheeler Additions & Renovations:
- Completed west detention pond
- Completed drywall, ceiling tiles, painting in studio/media area and clinic
- Began concrete curbs and gutters for parking lots
New Administration Building and Alt Ed/Resource Center:
- Installed new NIPSCO utility poles
- Continued earthwork for back drive
- Began installing new storm system, digging footings and piers, pouring footings and piers
Board Report
MacArthur Elementary
July 2022
Taft Middle School
- Roofing, ceiling piping, interior metal stud walls, pouring slab in academic wing
- Began setting structural steel in auditorium
- Began brick veneer on main gymnasium
Crown Point High School
- Completed ductwork in satellite kitchen area
- Completed boiler installation
- Completed foundations for performing arts addition
- Began re-roofing of auditorium and hanging mechanical piping to new addition
Timothy Ball Elementary
- Completed load bearing CMU walls for classroom addition
- Completed all underground site utilities
- Began structural steel and brick veneer for classroom addition
MacArthur Elementary
- Completed demolition and installed storm structures/piping in Southeast parking lot
- Established and grading building pad for new classroom addition
- Continued demolition of front office, administration, clinic, and music rooms
Wheeler Middle School
- Completed demolition of studio/media area
- Completed interior metals suds in studio/media area
- Continued site work for new parking lots
Alternative Education and Admin Building
- Completed demo of existing parking lot and underground utilities
- Completed building pad
- Began earthwork for back drive
June 2022
New Robert A. Taft Middle School:
- Began exterior sheathing of academic wing
- Began cutting and placing stone on west parking lot
- Continued roofing of academic wing
- Completed laying CMU exterior walls for main gymnasium
High School:
- Started sanitary plumbing underground rough-ins for classroom addition
- Completed digging and pouring footings for athletic addition
- Installed new boilers
- Continued hanging mechanical piping in fieldhouse
Timothy Ball Elementary School:
- Started site demolition of east side of school
- Began work on site utilities on east side
- Began prep for west parking lot
- Poured footings for classroom addition
- Completed prep for classroom addition slab on grade
MacArthur Elementary School:
- Began demolition of southeast parking lot
- Began demolition of administration area
- Began demolition of mechanical, electrical, and plumbing systems in Unit B area
Timothy Ball east side - where gymnasium and preschool wing will be added
MacArthur Elementary
May 2022
Board meeting update begins at 35 minutes
- The bid package for the alternative education and program building as well as new admin building was approved. These will be on the site of the current Taft Middle School. Bids came in roughly two million dollars below budget.
- Other projects continue to move forward on time.
- Taft building: admin and cafeteria sections have started (steel)
- CPHS: concrete poured in courtyard
- Timothy Ball: grading of site and demo of old playground. Demo of old canopies and rerouting utilities where needed.
April 2022
- Bids were approved for construction work at Col. John Wheeler Middle School
- Dr. Terrill thanked the many local companies who have placed bids for our many projects, as well as Skillman and Gibraltar for their continued partnership, hard work, and attention to budget and detail as we move forward. Also thank you to attorney Cheryl Zic for her help.
March 2022
March 2022 Board Meeting - begins at 38:20
Timothy Ball and MacArthur Elementary
- Bids awarded for both projects
- Work begins early summer
Taft Middle School
- Continues on schedule
- Steel for administration section of building begins soon
- Exterior masonry for main and auxiliary gyms has started
CPHS
- Crane delivery and construction to begin work inside courtyard
- Masonry in academic wing will begin soon
Academic wing at the new Taft building
CPHS academic wing location
February 2022
February 2022 board meeting - building update begins at 31:00
Additional Projects
- Because of the successful bond sale earlier in the school year, additional money is available to expand some of the capital improvement projects. The board approved these. You can find more information in our winter edition of "We Are CP".
MacArthur and Timothy Ball Elementary Schools
- These projects will go to bid for contractors in early March with the tentative plan to award those bids at the March board meeting.
CPHS
- Work is starting on the academic wing after the final permitting process was finished. At the end of construction, 30 classrooms will have been added to CPHS.
- Construction will begin inside the courtyard next month, expanding the guidance and admin office areas.
New Taft Middle School
- The steel delivered last month is now place. You can see the shape/size of the academic wing of the building in the video below.
January 2022
January 2022 meeting - starts at 28:45
- 12 truckloads of steel arrived at the new Taft site and are being put into place. The building is starting to look like a building!
- CPHS has started some demolition on the south side of the building.
- Projects for Timothy Ball and MacArthur Elementary Schools will be bid in the coming months.
November 2020 - December 2021
- November 2021
- October 2021
- September 2021
- August 2021
- July 2021
- June 2021
- May 2021
- April 2021
- March 2021
- February 2021
- January 2021
- Dec. 14, 2020
- Dec. 7, 2020
- November 2020
November 2021
November Board meeting- update begins at 1:32:00
- Construction will begin soon at CPHS. Mr. Gianfermi shared the plans with the board. The timeline for construction at CPHS goes through the winter of 2024. Included in the renovations:
-
Addition of 25 new classrooms and 5 new science labs
-
Upgrade art, PLTW/robotics, and career/technical education spaces
-
Expand cafeteria and upgrade food service program
-
Update media center
-
Fill in courtyard to expand admin and guidance area
-
Widen high-traffic hallways
-
Add rehearsal space to performing arts wing
-
Add indoor physical education space and update fitness lab
-
October 2021
October 2021 Board Meeting- update begins at 49:20 and again at 1:01:46
- The second round of bids for construction of the new Taft Middle School were approved by the board. Mr. Katsouros noted that we had a lot of participation from local contractors. This round of bids included a number of items such as masonry, plumbing, electrical, roofing, flooring, etc. The structural steel bid was previously completed in the summer.
- Dr. Terrill noted that the district is proud to be utilizing many local contractors and trades organizations so that this project supports our local economy and community members.
- The district had a successful bond sale for the project. The rate will allow us to complete all of the scheduled projects while also leaving room for other issues that may arise. By financing the construction through bonds, residents of the district will NOT see any increase in their taxes.
- Bids for construction work at the high school will happen in early November, with the goal of approving those bids at the November board meeting.
- Planning for Timothy Ball Elementary and MacArthur Elementary is in the final stages. The goal is to bid these projects in late winter.
September 2021
September '21 meeting - update begins at 59:30
- Work at Taft continues to proceed as quickly as the weather allows. By early November it is anticipated that the base of the building will be poured, and steel will go up the beginning of next year.
- High school design plans are nearing completion after gathering input from staff.
- MacArthur and Timothy Ball design plans are also nearing completion.
August 2021
August '21 meeting - begins at 59:20
Development at the Taft site has started. Crews are preparing the site for foundation.
July 2021
June 2021
June 2021 - begins at 23:00
- First bid package was approved and information about those bids, particularly the building's steel, were provided by Skillman Corporation
- Underwriting agreement for the bond sale was approved
- Depending on cash flow, this is likely to happen late fall or early 2022
May 2021
May 2021 - begins at 39:50
- Approval to issue bonds for the project is given
- Resolutions passed for initial steps of the project
April 2021
April 2021 - begins 47:35
- Dr. Terrill shares the location of the future Taft Middle School site
- Preliminary site layout and conceptual building design are shown (see Program & Design Presentation document)
March 2021
March 2021 - project info begins at 47:50
- Additional designs and site maps of the building are shared
- Construction updates indicate that ground will be broken at the site this summer
February 2021
February 2021 - project info begins at 16:40
- A design committee has been established, which includes secondary administrators throughout the district as well as our director of buildings and grounds.
- The location of the new Taft Middle was announced, along with the rationale for choosing the site. Location will be at the corner of 121st Street and Gibson Avenue.
- A proposed - not definite - site layout was shared as an example of the amenities the new school will have.
January 2021
January 2021 - project info begins at 1:04:00
- The remonstrance period for the project has now passed.
- Site recommendations will be brought to the board soon so that the project can stay on schedule.
Dec. 14, 2020
December 14, 2020 - Second Public Hearing
- Attorney Zic reviews the process for approving a capital project, including the requirement to hold a public hearing and other additional steps
- Dr. Terrill reviews the rationale, proposed capital improvements, and timeline of the project
- CFO Katy Dowling and a representative from Baker Tilly (advisors) review the financial aspects of the project, including total estimated costs and how it can be funded without a referendum.
- Public comments were heard by the board.
- The board unanimously approved the capital improvement project as presented.
Dec. 7, 2020
December 7, 2020 - First Public Hearing
- Attorney Zic reviews the legal procedures for holding public hearings for capital projects
- Dr. Terrill provides an overview of the project including the rationale, details about what the project will include, the project timeline, and benefits.
- CFO Katy Dowling reviews the financial components of the project, including the estimated cost and explanation of no funding via a referendum.
- Public comments were heard by the board.
November 2020
November 2020 - project info begins at 26:00
- Dr. Terrill provides the board with an overview of the project and the work done in previous years to prepare for it.
Frequently Asked Questions
- Will residents see an increase in taxes?
- Why is the new middle school being built near Winfield?
- What will happen to the old Taft building?
- How is this project preparing for the population growth in Crown Point?
- What is the timeline for this project?
- The current Taft enrollment is around 1,100 and the new building will hold just over 1,400. Is this enough of an increase?
- Why aren’t we keeping all of the old Taft?
- Why are we adding on to CPHS and not building a second high school in Winfield?
- Why do we need a new administration building?
- I’ve heard redistricting will happen alongside construction. Where can I find more information?
Will residents see an increase in taxes?
Why is the new middle school being built near Winfield?
The location of the new Taft was chosen out of three properties already owned by CPCSC, purchased a number of years ago. Only two of those sites were large enough to fit a middle school that addresses our growing population. Out of those two, the chosen site in Winfield could best accommodate an appropriate site layout and adequate traffic flow, including room for buses and access for first responders in an emergency.
What will happen to the old Taft building?
How is this project preparing for the population growth in Crown Point?
What is the timeline for this project?
The new middle school will break ground in the summer of 2021, with a goal to open in the fall of 2023.
Tentative construction will begin at CPHS in December of 2021, at Timothy Ball in February of 2022, at MacArthur in March of 2022, and at Wheeler in May of 2022. These timelines may of course shift based on construction, available materials, weather, etc.
All projects are scheduled to be finished by 2024.
The current Taft enrollment is around 1,100 and the new building will hold just over 1,400. Is this enough of an increase?
Yes. In addition to the extra space at Taft, Col. Wheeler Middle School is also expanding. In the redistricting process, enrollment between the two schools will be balanced. With these steps combined, we are making room for hundreds of new middle school students. Demographic studies also show that while the Crown Point Community is growing, our student population is not growing as fast as some might assume (see our FAQs on the redistricting page for more information).
Why aren’t we keeping all of the old Taft?
Why are we adding on to CPHS and not building a second high school in Winfield?
Two high schools would mean a significant drop in the academic opportunities available to our students. At first glance, some people may think building another high school is an option. However, imagine the number of facilities and programs that would have to be split between two buildings. For example, we could not provide double the facilities and staff for our valuable CTE programs like auto, construction, etc. We would have to somehow split our theater, music, and art department staff and resources. Most of our AP and Dual Credit classes are taught by one specialized, licensed teacher. The financial and operational cost of two high schools is not an option at this time. Across the Midwest, teacher shortages are also affecting schools. While CPCSC has been fortunate that these shortages have not affected our district, we don’t want to create a situation where it could be an issue.
Why do we need a new administration building?
The administration team is currently housed in three separate buildings throughout the district. The current building on North Street is out of space. We have turned what used to be storage spaces into offices. When the Learning Center becomes part of Col. Wheeler Middle School, we will lose nearly a dozen office spaces and professional development/meeting rooms. The Support Service Center on Summit Street is likewise out of space and it is not ADA compliant. Building a new administration center addresses all of these issues. The SSC on Summit Street will remain our transportation hub. It has not been determined yet what we will do with the ASC building on North Street.
I’ve heard redistricting will happen alongside construction. Where can I find more information?
All of the information about redistricting can be found at www.cps.k12.in.us/redistrict23.